项目概述
由于疫情影响新疆生鲜农产品销售渠道受阻,政府迫切需要采取措施帮助农民将农产品运销出去。
As the epidemic affects Xinjiang’s fresh agricultural products sales channels are blocked, the government urgently needs to take measures to help farmers sell their agricultural products.

由第三方物流公司设计项目整体方案,通过大数据分析预测各省市的市场需求,对新疆阿克苏地区进行实地考察后,将通过检疫的生鲜农产品以大宗货物的运输模式送至各省市,实现新疆阿克苏地区生鲜农产品的正常销售,稳定该地区经济发展。
The overall plan of the project is designed by a third-party logistics company, and the market demand of various provinces and cities is predicted through big data analysis. After a field visit to the Aksu area of Xinjiang, the fresh agricultural products that have passed quarantine are sent to the provinces and cities in bulk cargo transportation mode to realize Xinjiang The normal sales of fresh agricultural products in Aksu area have stabilized the economic development of the region.

构建新疆阿克苏生鲜农产品第三方物流直销管理系统、生鲜农产品冷链仓储设施建设以及标准化基础设施设备(塑料托盘、PEF周转箱)的采购等。
Construct a third-party logistics direct sales management system for fresh agricultural products in Aksu, Xinjiang, the construction of cold chain storage facilities for fresh agricultural products, and the procurement of standardized infrastructure equipment (plastic pallets, PEF turnover boxes), etc.
工作分解详情表
活动排序
工期估算
进度计划制定
进度控制
控制方案:
在项目进行试运行之后,因为新疆疫情不断有确诊案例,根据国家政策,在新疆运出的农产品需要更严格的检疫,所以在整个供应链的调整维护阶段需要多需要了一天,以严格把控供应链的安全稳定。也正是因为疫情的反复,项目验收阶段,供应链各个环节都须进行检疫,相关人员也都需要核酸检测,以确保防疫工作的顺利推进。所以在这两个阶段,项目的实际完成时间都延后了。
这里采取的纠偏措施主要是,目前处于项目的收尾阶段,为了保证项目后期按期竣工,所以在项目的迭代运营优化阶段,压缩了时间,将运营迭代优化的工作,在前面的工作中就不断派人跟进,增派人手管理项目的运营,使运营方案一直处于比较与现实状态相匹配的状态,给后续的优化任务减轻负担。
After the trial operation of the project, because the Xinjiang epidemic situation continues to have confirmed cases, according to national policies, agricultural products shipped out of Xinjiang require stricter quarantine, so it will take an extra day to adjust and maintain the entire supply chain to strictly control Security and stability of the supply chain. It is precisely because of the repeated epidemics that quarantine is required at all links of the supply chain during the project acceptance phase, and relevant personnel also need nucleic acid testing to ensure the smooth progress of the epidemic prevention work. So in these two stages, the actual completion time of the project was delayed.
The corrective measures taken here are mainly that it is currently in the final stage of the project. In order to ensure that the project is completed on schedule, in the iterative operation optimization stage of the project, the time has been compressed to optimize the operation iteratively. People follow up, and additional personnel are assigned to manage the operation of the project, so that the operation plan has always been in a state that matches the actual state and reduces the burden on subsequent optimization tasks.